Road work in Gaibandha progressing fast

Sumel Sarker

Gaibandha Map

Road work in Gaibandha progressing fast

13 December 2015, Nirapad News: Widening and maintenance work of 7 km long Badiakhali-Jumarbari Road via Bonarpara under Saghata upazila in the district has been progressing fast.

Local Government Engineering Department (LGED) is implementing the work at the cost of TK 1.47 crore under Rangpur Divisional Development Project funded by government of Bangladesh, office sources said.

Upazila engineer of LGED M. Sabiul Islam said over 50 percent work had already been completed and the rest would be finished by mid January, it was expected.

Executive engineer of LGED here Maksudul Alam said with the completion of the work different types of vehicles particularly the motorized ones would cross the road easily.